Home > Industry Topics > Additional Industry Topics > Partnering Case Studies > The Bonneville 2nd Powerhouse
The
Bonneville 2nd Powerhouse
Juvenile Fish
Bypass Improvements
North Bonneville, Washington
Partnering Lesson:
Project Description
The project
included construction of a two-mile-long pipeline,
modifications to the fish collection system in Bonneville
Dam's 2nd Powerhouse, and construction of buildings for fish
monitoring and tagging. The contract was awarded for $28.5
million. Work began in December 1997 with a completion date
of March 15, 2000, but was completed three months ahead of
schedule.
Project Challenges:
Issue
1 - Submittals:
Because
of the work schedule during the short winter months,
the Contractor's staff and the Government personnel
made submittals a high priority. In the first six
months of construction, the project went ahead of
schedule, which enabled the early completion date.
Issue
2 - Preparatory Meetings:
As part
of the three-phase CQC process, the Quality Control
personnel, subcontractor foreman and the Government
Quality Assurance Representative met for each
definable feature of work. On some key features of
work, Design Engineers also participated to add
information about the intent of the plans and specs
and clarify the specified requirements. The
designers also could explain any flexibility in the
requirements.
Benefits of Partnering:
Stakeholders:
U.S. Army Corps of Engineers Balfour-Beatty Construction,
Inc. National Marine Fisheries Service