| Project |
Project Description |
184 Family Housing Unit
Altus AFB, Altus, OK |
This $22 million Air Force design–build military family
housing project included the design and construction of 184 single–family,
detached, and duplex homes on 75 acres as well as play areas, a two–mile
jogging track, and an 18–hole golf course, and extensive landscaping. |
Base Realignment & Closure Project
Fort Leonard Wood, MO |
Hensel Phelps and 74 subcontractors logged 2,026,517 man–hours,
placed 45,000 cubic yards of concrete, and laid 625 miles of cable. Each
individual project had its own design firm, drawings, specifications,
submittal register, RFI log, and change estimate log. Both the metric
and imperial systems were used. |
The Bonneville 2nd Powerhouse
North Bonneville, WA |
The project included construction of a two–mile long pipeline,
modifications to the fish collection system in Bonneville Dam's 2nd Powerhouse,
and construction of buildings for fish monitoring and tagging. The contract
was awarded for $28.5 million. Work began in December 1997 with a completion
date of March 15, 2000, but was completed three months ahead of schedule. |
Sam Rayburn Spillway Modification
Jasper, TX |
Project entailed replacement of an existing spillway with
new labyrinth weir and spillway with a total length of 7,380 feet. Included
excavation for new approach channel, stilling basin and discharge channel,
structural concrete, and a relocated road 6,315 feet long. |
Dover Air Force Base
Dover, DE |
Philadelphia District was the new design and construction
agent for the Air Mobility Command (AMC) Military Construction program
at Dover Air Force Base. |
Tertiary Waste Water Treatment Facility
Ft. Dix, NJ |
Demolition of an existing facility and construction of
a 4.6 MGD facility consisting of: ten new structures; a state–of–the–art
Bardenpho Aeration tank system; 48,000 liner feet of 48" and 24" force
main; installation of mixers, clarifiers, sludge–handling and filter
equipment; and an 80–acre land application site. |
Units 5 and 6 Rehabilitation
Johnstown, PA |
The project consisted of the repair or replacement of
existing walls in Johnstown. These walls were constructed in the late
1930s and were not stable under current design criteria. |
99th RSC Headquarters and OMS/AMSA Facilities
Pittsburgh, PA |
The project was the development of an RFP for building
a 137,000 sf major training center on 35 acres. The center included administrative
spaces, classrooms, an assembly hall, an arms vault, physical examination
areas, and associated support spaces, as well as other related buildings. |
Airport Runway Project
Philadelphia, PA |
Philadelphia District organized an interagency partnering
team in conjunction with processing a DA permit application for expansion
of the Philadelphia Airport. |
Ashland II Soil Remediation
Tonawanda, NY |
Ashland II was a FUSRAP soil remediation project with
numerous stakeholders having varied expectations. Complicating issues
was a rigorous completion schedule to use as a program execution indicator
for successful project completion. |
Breakwater Major Rehabilitation
Burns Waterway Harbor
Porter County, IN |
This project provided for the placement of a new 4000–foot
long submerged rubble mound breakwater, located 75 feet from the existing
breakwater. This structure was built with 518,000 tons of stone in four
layers of increasing size up to five–ton stone. |
Degray Lake and Lake Greeson – Repair and Project Roads
Clark and Pike Counties, AR |
The project was to repair existing failed pavement areas,
place granular base courses, place asphalt surfaces, place granular shoulder
courses, remove and dispose existing pavement, create pavement markings,
and perform environmental protection at all sites. |
Differential Global Positioning System (DGPS), Site Establishment
Reedy Point, DE |
A new DGPS site at Reedy Point, Delaware was built to
integrate into the Nationwide DGPS network, which is operated and maintained
by the US Coast Guard. |
DuPont Chambers Works
Deepwater, NJ |
This 700–acre active chemical plant was previously identified
by the Department of Energy as a Formerly Used Sites Remedial Action
Program (FUSRAP) site. |
Fuse Plug Spillway Modification
Center Hill Dam |
The project schedule included milestones that coincided
with flood seasons. During excavation of the existing saddle dam, which
was later replaced with an erodable fuseplug, a calculated risk factor
was built into the construction sequence. |
Glen Foerd Historic Property
Philadelphia, PA |
The project consisted of repairing and rehabilitating
a 100+ year–old riverwall protecting the historic Glen Foerd property
from the erosive forces of the Delaware River and Poquessing Creek. |
Local Flood Protection
Cedar Falls, IA |
The construction involved a flood control project under
the Continuing Authorities Program that provided flood protection to
the city of Cedar Falls, Iowa. No flood protection existed between the
river and the town's business district. |
Lock and Dam No. 25
Lock Dewatering/Embedded Metals
St. Louis District |
The Lock rehabilitation was the installation of a deep
well watering system beneath the lock floor, the installation and removal
of the lock bulkheads, and the design, installation, and operation of
an ice control system. |
| Mississippi
River O&M & EMP Program Contracts |
There are multiple marine construction projects along
225 miles of the Upper Mississippi River from Guttenberg, Iowa, upstream
to Minneapolis, Minnesota. The projects range from a small rockfill slope
repair to a $4.1 million EMP project at a National Wildlife Refuge. |
Whole Barracks Renewal
Fort Riley, KS |
The $50 million project included the demolition of old
barracks and the construction of new barracks, company operations facilities,
soldier community buildings, and a dining hall. |
Maintenance Support Facility Seawall Upgrade Case Study
NAS North Island, San Diego, CA |
This project was designed to provide repair and maintenance
facilities for nuclear powered aircraft carriers. The project consisted
of an 80,000 sf two–story main building containing offices and a warehouse.
This building was constructed of metal wall panels on top of concrete
tilt–up panels clad to a structural steel frame on the exterior with
masonry walls up to 40 feet high on the interior. Three additional metal
storage buildings were also constructed. |